Inspection of Construction in Soi 18/2

0
245
Inspection of Construction in Soi 18/2
Inspection of Construction in Soi 18/2

Mr. Nopporn Wuttikul, Mayor of Hua Hin, along with Mr. Montree Chuphu, Deputy Mayor of Hua Hin and staff of the Water Supply Department inspected the area of Soi 18/2 Hua Hin, to follow up the progress of the reinforced concrete road construction drainage project. This project involves a reinforced concrete road with a width of 3.2 metres and a length of over 300 metres with a drainage system of 0.60 metres in diametre and also small sumps on both sides of the road. The total length of the project covers over 600 metres. The project has a budget of 3,000,000 THB and is expected to be completed by December.